Production Lead Time using Routings
The production lead time if you are using routings in Microsoft Dynamics NAV is the sum of the lead times for the operations that each can have 5 different time components; queue time, setup time, run time, wait time and move time. In addition to the production lead time is the safety lead time defined on the item or stockkeeping unit card of the product being produced; this adds a slack time between the scheduled ending time for the last operation and the due date of the production order. The below illustrates the different times and how they together makes up...